45 minutes ago, Stone Cold said:

Sorry once contracts are made price cant and shouldnt be allowed to go up or down.  Its a get f#&%ed stay f#&%ed world and once you are quoted with a contract theres no going back.

 

Every person who has built a house over the past 18ish months will tell you that what you're saying is wrong. When material cost goes up, the cost to build your structure does as well. You can't expect the contractor(s) to take a $15M hit...

  • Plus1 2
Link to comment

Yep, we have multiple projects going on at our school.  Just met with our GC last week about increases.  One project we were working on, the vendors only guaranteed quotes for 10 days.  30 is the norm I have seen.  We have a HVAC project my superintendent kept putting off.  Initial quote was 40K, by the time he accepted it was 54K.

 

We have a $20 million addition happening.  By the time permitting and bids go through, we will break ground in July of August.  We will start buying steel in February and store it in a warehouse somewhere.

 

Crazy times!

Link to comment

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

  • Recently Browsing   0 members

    • No registered users viewing this page.

Visit the Sports Illustrated Husker site



×
×
  • Create New...